Braindump2go Microsoft 70-178 Practice Tests Latest Questions Free Share (11-20)
Do you want to pass Microsoft 70-178 Exam ? If you answered YES, then look no further. Braindump2go offers you the best 70-178 exam questions which cover all core test topics and certification requirements. All REAL questions and answers from Microsoft Exam Center will help you be a 70-178 certified!
Vendor: Microsoft
Exam Code: 70-178
Exam Name: Microsoft Project 2010, Managing Projects
Keywords: 70-178 Exam Dumps,70-178 Practice Tests,70-178 Practice Exams,70-178 Exam Questions,70-178 PDF,70-178 VCE Free,70-178 Book,70-178 E-Book,70-178 Study Guide,70-178 Braindump,70-178 Prep Guide
QUESTION 11
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource.
What should you do?
A. Update the base project calendar.
B. Change the working time for the resource.
C. Change the maximum units for the resource.
D. Assign the resource only to tasks that are scheduled on the working days.
Answer: B
QUESTION 12
Your project has Subject Matter Experts (SMEs) who are consulted for each task.
You need to create a single field that includes a list of SME names that can be associated with each task.
What should you do?
A. Create a task custom field that includes a lookup table custom attribute.
B. Enter the list of SME names on the Resource tab of the Task Information window.
C. Create a project custom field that includes a lookup table custom attribute.
D. Create a resource custom field that includes a lookup table custom attribute.
Answer: A
QUESTION 13
You want to print the Gantt Chart view of your project.
You need to hide the Gantt chart legend.
What should you do?
A. Edit the view.
B. Edit the Bar Styles dialog box.
C. Edit the layout.
D. Edit the Page Setup dialog box.
E. Edit the Text Styles dialog box.
Answer: D
Explanation:
In Page Setup, on the Legend tab, set ‘Legend on’ to ‘None’.
QUESTION 14
You use Project Professional 2010 to manage a construction project.
Different members of the project team frequently modify a blueprint file.
The file is saved in a Microsoft Office SharePoint document library.
You need to access the file from within the project schedule.
What should you do?
A. Add a hyperlink.
B. Use the Links Between Projects tool.
C. Use the Sync with Tasks List feature.
D. Use the Save to SharePoint feature.
Answer: A
QUESTION 15
The milestones in your project schedule represent the end of phases.
You need to change the background color of the cells of the milestones to blue.
What should you do on the Format tab?
A. Select Text Styles, and then select Milestone Tasks.
B. Select Layout, and then select Show drawings.
C. Select Drawing, and then select Text Box.
D. Select Column Settings, and then select Milestone.
E. Select Bar Styles, and then select Milestone.
Answer: A
QUESTION 16
You receive a Microsoft Outlook e-mail message that contains the following task outline:
– Establish corporate internal communications process.
– Find out the regional and country divisions’ communications process.
– Plan communication methods, logistics, and timings.
– Establish regional and country communications to sales, marketing, and management.
– Find out the internal systems that must respond to the campaign.
– Create communications plan.
– Identify internal training requirements.
– Develop internal training.
– Organization of internal communications and training completion.
You need to incorporate the task outline into your project plan. What should you do?
A. Use the Bulk Import tool from the Project 2010 Solution Starters toolkit.
B. Copy and paste the task outline into the Task Sheet view of Project 2010.
C. Use the Task Inspector feature from Outlook.
D. Use the Import Outlook Tasks option.
Answer: B
QUESTION 17
You attempt to print the task table and Gantt chart horizontally.
However, the task names do not appear on each printed page.
You need to ensure that the task names are printed on each page.
What should you do?
A. Modify the settings in the Column Settings dialog box of the Task Name column.
B. Select the Task Name column and click Print.
C. Select the Task Name column and click Add to Timeline.
D. Modify the settings in the Field Settings dialog box of the Task Name column.
E. Modify the settings in the Page Setup dialog box.
Answer: E
Explanation:
In Page Setup, on the View tab, Print first n columns on all pages.
QUESTION 18
The dates of your project are displayed in the long date format as Wed 09-01-28 12:33.
You need to ensure that the dates are displayed as 1/28/09.
What should you do?
A. On the Format menu, modify the settings in the Layout dialog box.
B. On the File menu, modify the settings in the Options dialog box.
C. On the Format menu, modify the settings in the Text Styles dialog box.
D. Modify the settings in the Field Settings dialog box.
Answer: B
QUESTION 19
You create a new Gantt Chart view.
You need to copy the view to a different project.
What should you do?
A. Use the Links Between Projects tool.
B. Use the Organizer tool.
C. Use the Save Views feature.
D. Use the Compare Projects feature.
Answer: B
Explanation:
The Organizer is a dialog box that allows you to copy custom elements (incl. views, reports, tables, filters, groups) between files, or between a file and the global template.
QUESTION 20
In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
– Tasks that are not started.
– Tasks in progress.
– Tasks that have finished.
– Total remaining effort for each group of tasks.
What should you do on the View tab?
A. Select Group by Complete and Incomplete Tasks, and then add the Remaining Work field to the table.
B. Select Group by Complete and Incomplete Tasks, and then add the Work field to the table.
C. Select Group by Active v. Inactive, and then add the Remaining Work field to the table.
D. Select Group by Active v. Inactive, and then add the Work field to the table.
Answer: A
Braindump2go Guarantee:
Pass-Certification 70-178 offers absolute risk free investment opportunity, values your timr and money! Braindump2go latest 70-178 Real Exam Dumps – Your success in 70-178 Exam is certain! Your belief in our 70-178 Exam Dumps is further strengthened with 100% Money Back Promise from Braindump2go!